Plot
Zoning values
Unit types (%)
Common stair
Save, share and get a PDF report
Save your project in the panel, share it by link and get a PDF report. Calculation and 3D draft are free; the PDF report costs 1 credit.
Save, share and get a PDF reportBuilding capacity
3D massing draft
Drag to rotate, pinch to zoom.
Plot and footprint
Tap an edge in the drawing to set the front (street-facing) side.
Regulation checks
CompliantFootprint areaPAİY Art. 4/1-cccc · PAİY Art. 20/3
Footprint 240 m². The smaller of the coverage-ratio area and the area left after setbacks is used (240 m²).
Source: PAİY Art. 4/1-cccc · PAİY Art. 20/3
CompliantFloor area ratio (FAR)PAİY Art. 4/1-tt · PAİY Art. 5/5
Built area within FAR 1200 m², FAR base 1200 m². Calculated on the net zoning plot.
Source: PAİY Art. 4/1-tt · PAİY Art. 5/5
CompliantFront setbackPAİY Art. 23/1-a
Entered 5 m. Unless the plan says otherwise the front setback is at least 5 m.
Source: PAİY Art. 23/1-a
CompliantSide setbackPAİY Art. 23/1-b
Entered 3 m. Unless the plan says otherwise the side setback is at least 3 m.
Source: PAİY Art. 23/1-b
CompliantRear setbackPAİY Art. 23/1-c
Entered 3 m. Unless the plan says otherwise the rear setback is at least 3 m.
Source: PAİY Art. 23/1-c
CompliantFloor heightPAİY Art. 28/1-c
In residential zones floor height is at most 3.6 m (4.00 m for buildings up to 3 floors excl. basement). Entered 3 m.
Source: PAİY Art. 28/1-c
CompliantClear height at least 2.60 mPAİY Art. 28/4
Habitable floors need at least 2.60 m clear height. With 3 m floor-to-floor, check this after slab thickness.
Source: PAİY Art. 28/4
CompliantCommon stair widthPAİY Art. 31/1-a
Common stairs and landings in housing must be at least 1.2 m. Entered 1.2 m.
Source: PAİY Art. 31/1-a
CompliantRiser height (with lift)PAİY Art. 31/2-a
With a lift, risers are at most 0.18 m. Entered 0.17 m.
Source: PAİY Art. 31/2-a
CompliantTread (2a+b)PAİY Art. 31/2-b
2a+b must be 60–64 cm and tread at least 0.27 m. Computed 62 cm, tread 0.28 m.
Source: PAİY Art. 31/2-b
CompliantMinimum room areas · 2+1PAİY Art. 29/1 · PAİY Art. 29/4
Each dwelling needs a living room (12 m²), bedroom (9 m²), kitchen (3.3 m²), bathroom (3 m²) and WC (1.2 m²). Net taken as 80% of gross: 76 m², required 37.5 m².
Source: PAİY Art. 29/1 · PAİY Art. 29/4
CompliantMinimum room areas · 3+1PAİY Art. 29/1 · PAİY Art. 29/4
Each dwelling needs a living room (12 m²), bedroom (9 m²), kitchen (3.3 m²), bathroom (3 m²) and WC (1.2 m²). Net taken as 80% of gross: 104 m², required 46.5 m².
Source: PAİY Art. 29/1 · PAİY Art. 29/4
InfoPlot assumed rectangularPAİY Art. 5/5
No plot geometry was loaded, so a rectangle was assumed from area and frontage. Load the plot by block/parcel for an exact footprint.
Source: PAİY Art. 5/5
InfoFAR-exempt areas max 30%PAİY Art. 5/8
Parking, shelters and technical rooms together cannot exceed 30% of the FAR base (360 m²).
Source: PAİY Art. 5/8
InfoSide and rear setbacks grow above 4 floorsPAİY Art. 23/1-ç
For a 5-floor building, 0.50 m is added per floor above 4. Side/rear used: 3.5/3.5 m.
Source: PAİY Art. 23/1-ç
InfoLift requiredPAİY Art. 34/1
Buildings with 4 or more floors including basement must have a lift (except single-unit homes). Count basements too.
Source: PAİY Art. 34/1
InfoNo dwellings in the atticPAİY Art. 40/7
The attic may only hold rooms linked to top-floor units and technical spaces.
Source: PAİY Art. 40/7
InfoParkingPAİY Art. 27/1-ç
Required parking follows the Parking Regulation (Official Gazette 22.02.2018, no. 30340) and the municipality’s parking rules. Parking areas are FAR-exempt.
Source: PAİY Art. 27/1-ç
Checks follow the official text: Planned Areas Zoning Regulation (Türkiye) (Official Gazette 03.07.2017, no. 30113). Last amended: Official Gazette 01.07.2026, no. 33297.
Estimated unit mix
| Type | Count | Gross m² | Total m² |
|---|---|---|---|
| 2+1 | 5 | 95 | 475 |
| 3+1 | 4 | 130 | 520 |
Continue with this plot
How is it calculated?
The footprint is the smaller of the coverage-ratio area and the area left after setbacks. The FAR base is plot area times FAR. The floor count is the smallest of the plan’s floor count, the height limit and FAR divided by footprint. Above 4 floors, side and rear setbacks grow by 0.50 m per extra floor and the footprint is recalculated.
If the plan sets no coverage ratio or FAR, the general rule of the regulation is applied and flagged in the checklist. Units are estimated by spreading the area within FAR, less a common-area share, over the unit types you choose.
Which checks are made?
Front, side and rear setbacks, the extra setback above 4 floors, FAR and FAR-exempt limits, floor height and clear height, the high-rise threshold, lift requirements, common stair width, riser height and the 2a+b rule, and minimum room areas in housing. Each check shows the article, paragraph and clause of the regulation.
Parking counts depend on municipal parking rules, so the tool points to the regulation instead of giving a number.
Does it replace an official permit project?
No. It is a pre-feasibility draft. The local zoning plan and municipal rules may differ. The permit project is prepared by a licensed architect and approved by the authority. The draft lets you talk in concrete numbers with landowners, developers and buyers.
Frequently asked questions
Which regulation are the checks based on?
The current text of the Planned Areas Zoning Regulation (Official Gazette 03.07.2017, no. 30113), including the amendment of 1 July 2026. Each check shows its article number.
Where does the plot boundary come from?
It is loaded from official land registry records by block and parcel. Without it, a rectangle is assumed from the area and frontage you enter, and this is flagged.
How do I choose the front side?
Tap the street-facing edge in the plot drawing. The front setback applies there, the rear setback to the opposite edge and side setbacks to the rest.
Is it paid?
Calculation, checks and the 3D draft are free. Saving, duplicating and sharing projects in the panel are free too; the PDF report costs 1 credit.
What if my municipality’s rules differ?
Enter the values from your zoning certificate; the plan and local rules come before the general rule. Always confirm with the authority.